1. An ORS staff member will burst the leak test letters from the database after having reviewed the leak test results. HP Techs, therefore, complete steps 2, 3, 4, 5, 6, 7, and 15.
  2. Click “Inventory” on top row
  3. Under Reports section select “Leak Tests”
  4. Select “AU Leak Test Letters”, "AU Leak Test Letters -  Radon Emanation" (for Radon Emanation letters), or "AU Leak Test Letters - Sources in Waste Room"
  5. Choose appropriate date range for which leak tests were conducted
  6. Click “View Report”
  7. Print a copy of each report to attach to the Work Order.
  8. From the report display, click "Email Burst"
  9. Select "Researchers/PIs"  from "Available Burst Groups"
  10. Click "Next"
  11. Select "Reports"  for category.
  12. Select "AU Leak Test Letters" or "AU Leak Test Letters - Radon Emanation" template.
  13. Select PI(s) to send report to by clicking the check box under the "Burst?" column or click "Select All"
  14. Click "Send"
  15. Print and complete the Work Order cover sheet from the Work Orders database.
    • Attach
      • Results printouts (from LSC, LB5100, etc.)
      • Copy of leak test letters from step 7 above
      • Sealed Source Leak Test History report
        • Follow steps 2 and 3 above, then select "Sealed Source Leak Test History".
        • Select the date range over which the leak tests were conducted.
        • For alpha leak tests, under "History Type" select "Leak Test" and "Radon Emanation Test", click "View Report", and print a copy. Write an indication on the printed report which results are the radon emanation results.
        • For beta leak tests, under "History Type" select "Leak Test - 6", click "View Report, and print a copy.
        • Repeat the four sub-bullets directly above for "Sealed Source Leak Test History - Sources in Waste Room".